Scheduled Timeline as of 12/12/14

IMG_1065 - Copy

                                                    Estimated

                                                  Completion

                                                           Date

Roof Dry In                                                  2/20/15

Framing                                                         2/23/15

Roof System                                                 4/20/15

Casework                                                       5/18/15

Hang Drywall                                               5/19/15

Paint Interior                                              6/04/15

Elevator Install                                          6/09/15

Kitchen Complete                                      6/09/15

Gym Floor                                                     6/25/15

Flooring/Tile                                               7/10/15

Playground Equipment                            7/14/15

Doors & Hardware                                      7/21/15

Substantial Completion                           7/30/15

Final Inspections                                        7/30/15

FF&E Install                                            7/13/15 – 7/31/15

Final Certificate of Occupancy               7/31/15

Owner Move in/Staff Arrival            8/03/15 -8/31/15