High School Update – August 4, 2015

Work is progressing at the High School, with the most visible changes happening to the front office and the entry vestibule. The old flooring has been removed, walls painted, new casework is being installed in the front office and electronic access controls are being added to several doors for better security. The current plan is to get the new flooring and casework installed in time for the Administrative staff to move back to their quarters by the week of August 17th.

In addition, new fencing and gates have been installed at rear of school, new ADA ramps to two modulars have been installed and new gutters to the main building have been installed.