CCMS Remodel Update – July 28, 2016

The hallways and lockers are being painted with a new color scheme and will be complete by next week.  Then the painters will move outside to paint the exterior of the building.  The top section of the brick chimney has been removed to be at a safer height while still operating efficiently.  The sidewalk on Second Street has been poured, and beginning next week the south parking lot will be repaved.  New sidewalks will be poured on Knowledge Street next week.

IMG_4094 - Copy

Hallways and lockers painted with new color scheme

 

IMG_4095 - Copy

IMG_3929 - Copy

Before top section of chimney removed (in case of seismic activity, this unnecessary top section could tumble)

 

IMG_4024 - Copy

After top section of chimney removed