Pioneer South/First Street Remodel – January 6, 2017

Carpet has been installed in the new IT office and offices by the front entry.  Almost all of the vinyl flooring has been installed in the rest of the building and most of the interior painting is completed.  The walk-in freezer and cooler for the Production Kitchen are being installed and all the new furniture for the building has been delivered.  The IT department moved to their space during Christmas break and is getting settled in.  The current plan calls for the Pioneer Alternative High School to move in during Spring Break.

img_4452-it-dept

IT Department getting settled in where the old library was

 

img_4460-new-vct-paint

Typical classroom with new flooring and paint

 

img_4483-freezer

Walk in freezer

 

img_4451-cafeteria

New flooring in cafeteria

 

img_4486-break-room

Future staff break room