Pioneer South – Exterior Work Completed July 2017

The exterior of the building has a new entry with ADA ramp, improvements to loading dock, stairways repaired or replaced, new exterior sunscreens installed, stucco repairs and painting of the building.  Below are some “before” and “after” pictures. Before   … Continue reading

img_4545-computer-lab

Pioneer South Open House – April 10, 2017

With the interior of the new Pioneer South building now complete and everyone moved in during Spring Break, a celebratory Open House was held on April 10th just prior to the district Board Meeting.  This building located on First Street, … Continue reading

img_4452-it-dept

Pioneer South/First Street Remodel – January 6, 2017

Carpet has been installed in the new IT office and offices by the front entry.  Almost all of the vinyl flooring has been installed in the rest of the building and most of the interior painting is completed.  The walk-in … Continue reading

img_4433-copy

Pioneer South/First Street Remodel – November 30, 2016

This project is well underway.  New flooring will be installed throughout the building including new plywood underlayment.  The front entry will have new exterior stairs and an ADA ramp as well as a security vestibule similar to the other schools … Continue reading

img_4435-copy

Crooked River Elementary (formerly Cecil Sly Elementary) – November 30, 2016

The new sidewalk from Second Street to the Stadium has been completed as well as the new breezeway that connects the two classroom wings.  Plans are being finalized to install irrigation and landscaping to the front of the school as … Continue reading

img_4340-after

It’s official; Crooked River Elementary sign completes the new front entry

Before remodel After remodel

IMG_4326 - New paint & striping

CCMS Remodel Update – September, 2016

New sidewalks have been poured on Knowledge and Second Street, the south parking lot has been repaved and striped and the new bus turnout has been completed along with new fencing on Second Street.  Also, the exterior painting has just … Continue reading

IMG_4280 - Front Entry

Crooked River Elementary Update (formerly Cecil Sly) – September, 2016

New front entry Front entry Administration area New student desks and chairs throughout the school Music Room – all new flooring, paint and chairs Cafeteria – new windows and flooring Computer Room – all new desks and chairs Library dedicated … Continue reading

IMG_4298 - Copy

Powell Butte Update – August 31, 2016

The new roof and window projects are now complete.  In addition to the new roof, the soffits, rafters and canopies have been pressure washed and painted and new snow guards were installed.  The new windows are insulated, energy efficient windows. … Continue reading

IMG_4197 - Copy

Crooked River Elementary Grand Opening

The Grand Opening of the new Crooked River Elementary was well attended on Thursday, August 18th.  Formerly known as Cecil Sly Elementary, the newly remodeled school has a brand new front entry that is much more inviting and has all … Continue reading