IMG_4326 - New paint & striping

CCMS Remodel Update – September, 2016

New sidewalks have been poured on Knowledge and Second Street, the south parking lot has been repaved and striped and the new bus turnout has been completed along with new fencing on Second Street.  Also, the exterior painting has just … Continue reading

IMG_4095 - Copy

CCMS Remodel Update – July 28, 2016

The hallways and lockers are being painted with a new color scheme and will be complete by next week.  Then the painters will move outside to paint the exterior of the building.  The top section of the brick chimney has … Continue reading

IMG_3897 - Copy

CCMS Remodel Update – June 22, 2016

Phase 2 of the Middle School remodel is in full swing inside and outside the building.  The boys and girls restrooms near the front entrance have been gutted, door frames throughout the building are being repaired, and a new fire … Continue reading

IMG_3147 - Front Entry

Middle School Update – September 3, 2015

Phase 1 of the Middle School remodel has been completed. This work included a new front entry with a larger canopy, new benches, bicycle rack, and better ADA access. In addition, the main office has a new reception window, front … Continue reading

IMG_2908 - Front Entry

Middle School Update – August 4, 2015

Phase 1 of the Middle School remodel will be completed before school starts on September 8th. The most noticeable changes will include the new canopy at the main entrance, new windows in the front office, and eventually new sidewalks and … Continue reading

IMG_2438 - Admin Windows

Middle School Update – July 2, 2015

The demolition to the front entry and administrative offices is completed and the remodeling is beginning. These front offices will get new windows and the entry will have a new awning as well as new ADA compliant sidewalks. This part … Continue reading

DSC_0261 - MS Gym Floor

Middle School Update – June 15, 2015

The main gym floor has been completed and looks beautiful. A minor correction will be made to the “CC” logo. Demolition work began this week at the entrance of the school including removing sidewalks and digging a trench across the … Continue reading

IMG_2303 - Copy

MS Gym Floor Update – 4/28/15

The new maple flooring has been laid in place over new sub flooring and the workers from A-Game Courts have just started nailing it to the sub floor. They started nailing the boards in the center of the gym and … Continue reading

DSC_0251 - Copy

Middle School Gym Floors to be Replaced – April 7, 2015

Demo work began today in the main gym to remove the old wood floor. The old floor will be replaced with a new maple floor including sanding, sealing, finishing and repainting the game lines. This is the original wood floor … Continue reading

Middle School Remodeling Contractor Selected

CS Construction, based in Bend, Oregon was selected as the CM/GC (Construction Manager/General Contractor) for this remodeling project on February 24, 2015.  Work has begun on developing a design concept with CS Construction, BLRB Architects, staff at the Middle School … Continue reading