Barnes Butte Elementary officially opens with Ribbon Cutting ceremony

On Friday, August 21, 2015 the community of Crook County showed their support for the opening of Barnes Butte Elementary. The ceremony opened with the NJROTC group from Crook County High School in the presentation of the flag. Jim Bates, Principal   Dr. Duane Yecha, Superintendent   Doug Smith, School Board Chair   Ribbon Cutting […]

You Are Invited to Grand Opening

Barnes Butte Update – August 4, 2015

Front Exterior Library Crooked River Pod Entrance Beaver Creek Pod Entrance Classroom in Lookout Mountain Pod Classroom in Big Summit Prairie Pod View from Classroom Cafeteria  

Barnes Butte Update – July 2, 2015

The flag at the new Barnes Butte Elementary has been raised. The contractors are currently working on the finishing work, which includes plumbing, electrical, flooring, carpentry, landscaping, paving, etc.

Barnes Butte Update – June 18, 2015

The gym floor is completed and looks beautiful. This was the view before the floors were covered with temporary protective panels until construction at the school is completed.  

Save the Date – Ribbon Cutting

Barnes Butte Elementary Update – May 15, 2015

Tours of the new school will be suspended after today’s tour at 3:30 due to electrical work that will make tours unsafe for visitors.  Friday tours may resume soon.  Watch for more information.  If you wish to join today’s tour, please email Jim Bates at Jim.Bates@crookcounty.k12.or.us.  

Barnes Butte Elementary Update – May 1, 2015

The exterior of the building and the grounds are starting to take shape The gym walls have been painted and the acoustical panels are being installed

Barnes Butte Elementary Update – April 3, 2015

A tour of the school is given by Jim Bates, who will be the Principal at Barnes Butte, each Friday afternoon. These tours are now open to the public every Friday afternoon at 3:30 pm (except April 17th). Please email Jim if you plan to attend one of these tours at Jim.Bates@crookcounty.k12.or.us. Please park on […]

Barnes Butte Elementary Update – March 3, 2015

The front entry is almost complete, the first of the glass is being installed in windows, sheetrock is going up, the masons have started to install the CMU (concrete masonry unit) veneer up to the tops of windows on the lower level and the roof is nearly completed. The orange color on the side is […]