Powell Butte Update – August 31, 2016

The new roof and window projects are now complete.  In addition to the new roof, the soffits, rafters and canopies have been pressure washed and painted and new snow guards were installed.  The new windows are insulated, energy efficient windows. Before   After

Powell Butte Update – June 30, 2016

The roof at Powell Butte is getting a huge facelift which has involved removing several layers of roofing material and replacing with a new metal roof on the sides and a new single ply roof on the top flat section.  In addition, all the soffits, rafters and canopies will be pressure washed and painted and […]

Powell Butte Update – September 8, 2015

Projects that were just completed include a new fire alarm system and new doors to the main entry and rear entry. In addition, new flooring was installed in the library. A new roof will be installed on the main building next spring or summer depending on the weather. Before After Before After New flooring in […]